Aug 26, 2024 7:36 PM - The Canadian Press

BC Hydro begins filling reservoir as Site C dam megaproject nears completion

Share On
bc-hydro-begins-filling-reservoir-as-site-c-dam-megaproject-nears-completion
BC Hydro says it will take between two and four months to fill the 83-kilometre-long reservoir, which will cover about 5,550 hectares of land while totalling about 9,330 hectares in surface area.(Photo: The Canadian Press)

BC Hydro says it has begun filling the reservoir created by the massive Site C dam project in northeastern British Columbia.

The provincial electric utility says in a statement that the filling of the reservoir is one of the last steps toward starting operations for the controversial dam project, located about 14 kilometres southwest of Fort St. John, B.C.

BC Hydro says it will take between two and four months to fill the 83-kilometre-long reservoir, which will cover about 5,550 hectares of land while totalling about 9,330 hectares in surface area.

The utility is warning people to stay away from the area of the reservoir for at least a year after it has been filled, citing possible unstable terrain and floating debris as potential hazards.

Construction of Site C was launched in 2015 under then-premier Christy Clark's BC Liberals government and has seen cost estimates spike from up to $6.6 billion in 2007 to $16 billion in 2021.

Multiple groups opposed the province's plan to complete the dam after the NDP formed government in B.C. in 2017, but former premier John Horgan said the dam needed to be finished despite his party not supporting the start of construction in the first place.

Horgan said at the time that cancelling the megaproject mid-construction would have meant laying off 4,500 workers as well as the loss of $10 billion in costs already sunk in building the dam, resulting in a 26 per cent increase in B.C. residents' hydro bills over 10 years.

The project had been opposed by groups such as the Peace Valley Landowner Association, Prophet River First Nation and West Moberly First Nations on both environmental and land-rights grounds.

BC Hydro says construction is now more than 85-per-cent complete, with the first power-generating unit on-site scheduled to begin operations in December.

When all six power generators are operational by fall 2025, BC Hydro says Site C will add 1,100 megawatts of electricity capacity while producing about 5,100 gigawatt hours annually about an eight-per-cent increase to the province's overall power supply.

BC Hydro says Site C will provide enough clean electricity to reliably power nearly 500,000 homes or 1.7 million electric vehicles when fully operational.

The provincial utility says the project also remains on track to be completed within the $16-billion budget established in 2021.

The idea of Site C a third dam on the Peace River in northeastern B.C. began decades ago but had been shelved in 1989 due to local opposition.

Latest news

CanadaNov 20, 2025

Indian national wanted in murder case arrested after being refused entry at Canada–U.S. border

U.S. border officials say a 22-year-old Indian national was taken into custody at the Peace Bridge crossing at Fort Erie after Canadian officers refused him entry over the weekend. The case is drawing renewed attention to cross-border screening practices that affect travel between Ontario and Western New York, a corridor frequently used by travellers from Ontario’s South Asian communities. According to a statement from U.S. Customs and Border Protection, the man – identified as Vishat Kumar – had previously entered the United States without authorization in 2024 and did not appear for a
chrystia-freeland-to-leave-parliament-for-senior-leadership-role-with-rhodes-trust-in-u-k
CanadaNov 20, 2025

Chrystia Freeland to leave Parliament for senior leadership role with Rhodes Trust in U.K.

Chrystia Freeland is preparing to leave federal politics next year as she moves to Oxford, England, to take up a senior leadership role with the Rhodes Trust. The educational charity confirmed that Freeland will become its next chief executive officer on July 1, overseeing one of the world’s most influential international scholarship programs. The organization administers the Rhodes Scholarship, which brings students from around the globe to study at the University of Oxford. Freeland’s appointment places her at the centre of an institution that has produced generations of leaders in publi
rain-and-snow-alerts-in-effect-as-coastal-and-northern-b-c-brace-for-strong-weather-system
BCNov 20, 2025

Rain and Snow Alerts in Effect as Coastal and Northern B.C. Brace for Strong Weather System

Environment and Climate Change Canada has issued a pair of weather alerts for communities along British Columbia’s north and central coast, warning that a strong frontal system could bring significant rain and heavy mountain snow through the end of the week. The agency says areas from Bella Coola through Kitimat may receive as much as 70 millimetres of rain, raising the risk of water pooling on roads and possible washouts near rivers and creeks. The system is expected to weaken by Friday, but officials caution that changing conditions may still affect travel across coastal corridors. While t
senate-approves-citizenship-reform-for-lost-canadians-as-advocates-raise-adoption-concerns
CanadaNov 20, 2025

Senate approves citizenship reform for ‘Lost Canadians’ as advocates raise adoption concerns

Federal legislation designed to address long-standing gaps in Canada’s citizenship rules has cleared the Senate and is expected to become law before a court-imposed deadline early next year. The bill aims to resolve cases involving so-called Lost Canadians – individuals born abroad to Canadian parents who were themselves born outside the country and who lost access to citizenship because of restrictive rules adopted in 2009. The changes come after the Ontario Superior Court ruled last year that the previous one-generation limit on citizenship by descent was unconstitutional. Under the upda
AlbertaNov 20, 2025

Alberta auditor says failed lab privatization left public with $109 million bill

Alberta’s auditor general says the province’s attempt to shift community lab testing to a private operator resulted in significant financial losses and gaps in government oversight. A new report from Auditor General Doug Wylie estimates taxpayers absorbed roughly $109 million after the privatization effort collapsed. Wylie’s review found that senior officials in government advanced the plan despite internal warnings that the projected savings were unlikely. He says weaknesses in record keeping, financial analysis and contract oversight contributed to the breakdown of the agreement with D

Related News